AES Ohio plans to install a second 345/69kV transformer at the Clinton Substation, located in Wilmington, Ohio.
This will also require the addition of three 345kV breakers to establish a ring bus, 69kV circuit breakers, and associated equipment. The project is needed to relieve operational loading and reliability concerns on the 69kV system in the area. Also, the project will help improve operational flexibility through the addition of the second transformer and line allowing AES Ohio to take outages in the area for maintenance while keeping a source into the Wilmington area. This project is also needed to help ensure deliverability of the planned solar generation expansions along the Stuart-Clinton 345kV corridor.
The Clinton Substation is located on 46 E Dalton Rd, east of SR-68, Wilmington, Clinton County, Ohio.

Estimated project schedule
July 2021 |
|
August 2021 |
|
October 2021 |
|
June 2022 |
|
Indicates the current project stage. |
During construction, customers should not notice interruption of their electric service. If an outage is required for a short period, the affected customer(s) will be notified before the outage to limit the inconvenience.
Visit the Ohio Siting Board website to view the application and for more information. The Case Number for AES Ohio’s Clinton 345 kV Extension Project is 21-0679-EL-BNR.
To contact AES Ohio about the project or request an electronic copy or hard copy of the application, please leave a message at 937-331-4314 or email aesohiotransmissionmaintenancegroup@aes.com. You will receive a response within 1-2 business days.