AES Ohio is proposing the construction of the Creekside 138 kilovolt (kV) transmission line.
Located both within the City of Sidney and Clinton Township, Shelby County, Ohio, the Project will consist of installing a new one-mile, new double circuit 138kV transmission line, tapping the Millcreek-Eldean 138kV line and terminating into a new distribution substation, named Creekside Substation. The transmission line will be installed west of Fair and Infirmary Roads, north of Schenk Road, near the intersection of Interstate 75 and Fair Road. The proposed project, in combination with other area improvements, will support increased load growth in the Sidney areas.
Frequently asked questions
The Creekside 138kV transmission line project is located near the intersection of I-75 and Fair Road, along Infirmary and Fair Roads, both within the City of Sidney and Clinton Township, in Shelby County, Ohio.
Estimated project schedule
November 2022 |
|
February 2023 |
|
July 2023 |
|
October 2023 |
|
Bold-italic text indicates the current project stage |
During construction, customers should not notice interruption of their electric service. If an outage is required for a short period, the affected customer(s) will be notified before the outage to limit the inconvenience.
Visit the Ohio Siting Board website to view the application and for more information. The case number for the Creekside 138kV transmission line project is 22-0947-EL-BLN.
To contact AES Ohio about the project or request an electronic copy or hard copy of the application, please leave a message at 937-331-4314 or email dpltransmissionmaintenancegroup@aes.com. You will receive a response within 1-2 business days.